Question

Problems 1) In the following network, manually level your resources so that you may not use more than nine laborers per day at any time. Activity ABCDEFGH-- ABCDEFG Activity J Duration (Days) 2 4 6 9 5 7 3 2) In the following network, try to reduce the maximum daily resource demand to less than eight laborers per day. Duration (Days) 6294750832 IPA 10 A A A B B, C D, E, F IPA Laborers A, B B D D, E C, F, G C, G H, I 3 2 4 3 4 2 4 Laborers 2 3 3 3 4 2 3 1 2 3 3) For the network in question 3, attempt to perform two modifications (i.e., delaying activities within their available float) to the schedule that can potentially smooth the resource distribution. Discuss how you know if the proposed changes actually improved the resource distribution via smoothing (show the calculation work).

Fig: 1