problems 1 in the following network manually level your resources so t
Question
Problems
1) In the following network, manually level your resources so that you may not use more than nine laborers per day at
any time.
Activity
ABCDEFGH--
ABCDEFG
Activity
J
Duration (Days)
2
4
6
9
5
7
3
2) In the following network, try to reduce the maximum daily resource demand to less than eight laborers
per day.
Duration (Days)
6294750832
IPA
10
A
A
A
B
B, C
D, E, F
IPA
Laborers
A, B
B
D
D, E
C, F, G
C, G
H, I
3
2
4
3
4
2
4
Laborers
2
3
3
3
4
2
3
1
2
3
3) For the network in question 3, attempt to perform two modifications (i.e., delaying activities within their available
float) to the schedule that can potentially smooth the resource distribution. Discuss how you know if the proposed
changes actually improved the resource distribution via smoothing (show the calculation work).