Question
Question 1 A project is made of the following activities: Duratio Predecessor ES EF LS LF slac Task n (s) k A 2 - BCDEFG 20 A с 5 A 20 C 17 B,C,D 11 D 2 E,F 1. Complete the table above - ES, EF, LS, LF, Slack 2. What is the critical path? What is the project duration? 3. Refer to the critical path you found in 2. Assum