The following questions are in reference to the plan set for the Post Ct and Simpson Pl Sewer

Replacement project. The plans can be downloaded or viewed on the course web page.

Please make your responses below each question in blue.

1. What document(s) shall all workmanship, materials and construction conform to?

2. What is the scale of the vicinity and location map?

3. What street(s) is construction work occurring on?

4. What type of facility is primarily being installed?

5. How many different scales are on this project? List them and where you can find them.

6. What does "DIP" mean? What does "AGG" mean?

7. What other existing utilities are present?

8. What is the total amount of PCC curb ramp to be installed?

9. What standard details trench backfill and paving?

10. Are there any utility removals shown? What is the material that is being removed?

11. How many feet are between SSMH No 1 and SSMH No 2 on Sheet 3?

12. What size and material is the new sanitary sewer main on sheet 4?

13. What is the description and elevation of survey control point 51 for Simpson Place?