Question

The information provided below is for Questions 1 through 5. Assume that you are pouring a wall that is 151 feet - 4 inches long by 16 Feet High by 16 inches thick wall, and the placement will be done using a crane and bucket. 1. Assume the bucket has a capacity of 2.5 cubic yards and it takes 7 minutes per cycle.What is the rate of delivery in cubic yards per hour? 2. What is the volume of concrete to be poured in cubic yards? 3. Assume that you can place 33 Cubic Yards per hour. How many hours are required to pour the cubic yards of concrete? 4. Assume that it takes 2.25 hours to pour the 151 feet - 4 inches long by 16 Feet High by 16 inches thick wall. What is the rate of pour in feet(vertical) per hour? 5. Assume the pour is using a concrete pump with a capacity of 635 cubic feet per hour.How many hours are required to pour the cubic yards of concrete?

Question image 1Question image 2Question image 3Question image 4Question image 5Question image 6Question image 7