Question

4) For the following project, draw the node network, perform the CPM calculations, mark the critical path, and complete the table (you don't need to fill this table in if you explicitly provide the information in your network). IPA Type Rel Lag ES EF LS LF TF FF Activity A B с D Duration 3526 A A ८८०० B с SS FF 3

Fig: 1