8, 9,and 10 is 40, 30, 20, 10, 50, 30, 70, and 20 units, respectively. The manufacturing and assembly lead times for PR-1, SA-12, and C-122 and the ordering lead time for M-4 are given below. Carry out the material requirements planning procedure for raw material M-4 required to manufacture component C-122 if one unit of M-4 is required to produce one unit of C-122. Lead time for assembling PR-1 =1 week. Lead time for assembling SA-12 = 1 week.|| Lead time for manufacturing C-122 = 2 week; 100 units on-hand inventory are given and 40 units are scheduled to arrive in period 2. Procurement lead time for raw material M41 week; 40 units on-hand inventory are available.